Haryana RERA: Recent Orders and Updates That Homebuyers Should Know
Haryana RERA issues orders and regulatory updates that affect homebuyers and real estate developers. This blog covers recent rulings and key regulatory developments. It also explains their impact on homebuyers, particularly in cases involving delayed possession, refund claims and builder defaults.
What can you do in such a situation? Can you claim interest for delayed possession? Can you ask for a refund or additional compensation?
The Haryana Real Estate Regulatory Authority (Haryana RERA) provides a legal framework to address such disputes between homebuyers and developers. Its recent orders have also highlighted several issues, including delayed possession, refund claims, builder non-compliance and compensation.
For homebuyers planning to purchase property in Gurugram, Faridabad, Panchkula or other parts of Haryana, keeping track of these decisions can help them understand their rights and the remedies available under the law.
Let's take a look at the latest Haryana RERA decisions and what they mean for homebuyers.
What Is Haryana RERA and How Does It Protect Homebuyers?
Haryana RERA is the state-level regulatory authority established under the Real Estate (Regulation and Development) Act, 2016. It regulates real estate projects and agents, monitors developer compliance and addresses complaints from homebuyers.The authority has two principal jurisdictions: Gurugram and Panchkula. Homebuyers can approach the relevant authority based on the location of their property.
The RERA Act gives homebuyers certain rights when a developer fails to meet contractual or statutory obligations.
For instance, Section 18 allows an allottee to seek a refund with interest if the promoter fails to complete or hand over the property within the agreed period, subject to the conditions under the Act. If the buyer chooses to remain in the project, they can claim interest for every month of delay until possession is handed over.
Section 19 also gives allottees the right to obtain project-related information, including sanctioned plans, completion schedules and other prescribed details.
These provisions form the basis of several complaints and orders passed by Haryana RERA.
Recent Haryana RERA Orders and Developments
Haryana RERA issues orders on various disputes between homebuyers and developers. These include delayed possession, refund claims and interest payments. Recent decisions also offer insights into how the authority protects buyer rights and enforces RERA provisions.Haryana RERA Orders 10.8% Interest for Delayed Possession in Godrej Meridien
In July 2026, Haryana RERA directed Godrej Real View Developers to pay interest at 10.8% per annum to two homebuyers who faced a delay in receiving their apartment in Godrej Meridien, Sector 106, Gurugram.The buyers, Madhu Chhabra and Pradip Chhabra, were entitled to possession by September 30, 2023. However, the developer failed to meet the agreed deadline.
The developer cited factors such as the Covid-19 pandemic and construction bans to explain the delay. However, the authority did not accept these reasons as sufficient grounds to avoid its obligations.
It directed the developer to pay interest for the delay period, from the due date until the offer of possession, along with an additional two-month period for the buyers to arrange the handover. The payment was to be made within 90 days.
What this means for homebuyers: Developers cannot automatically use construction disruptions or other external factors to avoid liability for delayed possession. The authority examines the circumstances and the contractual obligations before deciding whether such reasons justify an extension.
Haryana RERA Directs Agrante Reality to Pay 10.8% Interest to 26 Homebuyers
In September 2026, Haryana RERA, Gurugram, directed Agrante Reality Limited to pay delayed-possession interest at 10.8% per annum to 26 homebuyers in its Kavyam affordable housing project in Sector 108, Gurugram.The buyers had approached the authority after the developer failed to hand over their apartments within the stipulated period.
The authority held that the due date for possession was August 20, 2023. It considered the four-year completion timeline under Haryana's Affordable Housing Policy, 2013, while deciding the matter.
The order, passed on September 29, 2026, addressed all 26 complaints together, with Mohd Imran's complaint serving as the lead case.
What this means for homebuyers: Buyers of affordable housing projects can also seek relief when developers fail to meet possession deadlines. The completion timeline under the applicable housing policy and the terms of the allotment must be examined while assessing a delay claim.
Haryana RERA Awards Over ₹21 Lakh in Compensation for Delayed Possession
In March 2026, Haryana RERA directed Ramprastha Promoters and Developers to pay over ₹21 lakh in compensation to a homebuyer who had booked a flat in 2008 but did not receive possession as promised.The order followed a complaint filed by Nishant Mehra.
The compensation included ₹18.9 lakh for the loss of property appreciation, ₹2 lakh for mental harassment and ₹50,000 towards litigation costs.
An important aspect of this decision was the authority's observation that a refund of the amount invested does not automatically prevent a homebuyer from claiming additional compensation.
What this means for homebuyers: A delayed or failed housing project can cause losses beyond the money paid to the developer. Depending on the facts and evidence, a homebuyer may also seek compensation for other losses recognised under the law.
Gurugram Administration Starts Recovery Action Against 71 Builders
A RERA order in favour of a homebuyer does not always mean that the buyer receives the money immediately. Enforcement and recovery can also become challenges when developers fail to comply.In September 2026, the Gurugram district administration initiated recovery proceedings against 71 builders and developers over approximately ₹446 crore in outstanding RERA-related dues.
These dues arose from orders passed by Haryana RERA, including refunds, penalties and other amounts payable to affected homebuyers.
The administration initiated action to recover the outstanding amounts under Section 40(1) of the RERA Act, which allows certain amounts payable under RERA orders to be recovered as arrears of land revenue.
The action also included steps to freeze the bank accounts of defaulting developers.
What this means for homebuyers: Obtaining a favourable RERA order is an important step, but its enforcement matters just as much. The recovery action highlights the role of the district administration in ensuring that developers comply with orders and pay outstanding dues.
Haryana RERA Appellate Tribunal Clarifies When Buyers Can Claim Delay Compensation
Not every delay in receiving physical possession automatically entitles a homebuyer to delay compensation.In August 2026, the Haryana Real Estate Appellate Tribunal (REAT) dismissed an appeal filed by a homebuyer against Y.B. Builders and Nimai Developers.
The dispute concerned a possession offer issued on April 1, 2023. The buyer argued that delayed physical handover entitled her to compensation.
However, the appellate tribunal held that the developer had made a valid offer of possession before the stipulated possession date. It therefore upheld the Haryana RERA authority's decision denying delay compensation.
What this means for homebuyers: The date of physical handover is not the only factor in a delay-related dispute. The validity and timing of the possession offer also matter. Buyers should examine whether the developer has fulfilled the conditions required for a valid offer before accepting or challenging it.
What Can Homebuyers Do If a Builder Delays Possession?
The recent orders highlight the importance of understanding your rights before approaching Haryana RERA.If a developer fails to hand over possession within the agreed timeline, you can examine the remedies available under Section 18 of the RERA Act.
If you want to withdraw from the project, you may seek a refund with applicable interest and compensation, subject to the conditions under the Act.
If you want to continue with the purchase, you can seek interest for every month of delay until possession is handed over.
You should keep the relevant documents ready before filing a complaint. These may include:
- Builder-buyer agreement or agreement for sale.
- Allotment letter and payment receipts.
- Details of the promised possession date.
- Correspondence with the developer regarding the delay.
- Any possession offer or completion-related communication.
- Other documents that support your claim.
If either party is dissatisfied with the decision, an appeal may be filed before the Haryana Real Estate Appellate Tribunal, subject to the applicable provisions and timelines.
How to Check Haryana RERA Orders and Project Details?
Homebuyers can use the official Haryana RERA website to verify project registrations, check regulatory proceedings and access available orders and judgments.The authority maintains separate sections for Gurugram and Panchkula. Buyers should select the relevant jurisdiction before searching for a project or complaint.
Before booking a property, you should also verify its RERA registration number, registration validity, promoter details and approved project information.
If you are already facing a dispute, you can search the authority's orders and judgments to understand how it has addressed similar issues. However, an earlier decision does not guarantee the same outcome in another case. Each complaint depends on its facts, contractual terms and supporting evidence.
You can visit the official website of Haryana RERA for project details, orders, judgments and complaint-related information.
Recent Haryana RERA orders highlight the remedies available to homebuyers when developers fail to meet their obligations. From interest for delayed possession to refunds, additional compensation and recovery proceedings, these decisions show how the regulatory framework addresses different buyer grievances.
However, homebuyers should not rely only on the headline or outcome of an individual order. The agreement, possession timeline, project status and facts of the dispute all matter.
If you are planning to buy a property in Haryana or already own an under-construction apartment, following Haryana RERA's orders and checking project details can help you make informed decisions and understand your rights.
Disclaimer: The information presented by TOI Homes, part of The Times of India Group, is for general informational purposes only and does not constitute financial, legal, or investment advice. All data and insights are based on sources believed to be reliable but are not guaranteed for accuracy or completeness and are subject to change due to market conditions. The developer and associated entities are not liable for decisions made based on this information. Real estate investments involve risks, and buyers are advised to conduct independent due diligence and consult certified advisors before investing. TOI Homes does not endorse or promote any specific property or developer unless explicitly stated.